Formulas
- Ideal parts per hour = 3600 ÷ cycle time × parts per cycle.
- Real parts per hour = ideal × efficiency. Use availability × performance from your OEE data if you have it; otherwise be conservative.
- Max cycle time for a target = 3600 × parts per cycle × efficiency ÷ target per hour.
- Takt time = available time per day ÷ daily demand. The real cycle time (after efficiency) must be shorter.
Worked example
At the pre-filled 12 s cycle time with 1 part per cycle, ideal output is 3600 ÷ 12 = 300 parts/h; at 85 % efficiency that becomes 255 parts/h — 2,040 parts per 8 h shift, or 4,080 parts/day over two shifts.
Where cycle time really goes
Robot motion is often the smaller part of a cycle. Gripper open/close and vacuum build-up, waiting for a machine door or a CNC cycle, vision acquisition and processing, and safety-rated speed limits when people are nearby all add time. Measure a full cycle on a simulation or a trial cell before committing to an output figure.