Engineering tool

Cycle time & throughput calculator

Turn a cycle time into real output, including downtime — or work back from the output you need.

Work back from a target

Output

—parts/h
Ideal (100 % running)
—
Per shift
—
Per day
—
Max cycle time for target
—
Takt time for daily demand
—
Daily demand covered
—

Formulas

  • Ideal parts per hour = 3600 ÷ cycle time × parts per cycle.
  • Real parts per hour = ideal × efficiency. Use availability × performance from your OEE data if you have it; otherwise be conservative.
  • Max cycle time for a target = 3600 × parts per cycle × efficiency ÷ target per hour.
  • Takt time = available time per day ÷ daily demand. The real cycle time (after efficiency) must be shorter.

Worked example

At the pre-filled 12 s cycle time with 1 part per cycle, ideal output is 3600 ÷ 12 = 300 parts/h; at 85 % efficiency that becomes 255 parts/h — 2,040 parts per 8 h shift, or 4,080 parts/day over two shifts.

Where cycle time really goes

Robot motion is often the smaller part of a cycle. Gripper open/close and vacuum build-up, waiting for a machine door or a CNC cycle, vision acquisition and processing, and safety-rated speed limits when people are nearby all add time. Measure a full cycle on a simulation or a trial cell before committing to an output figure.